Our investment
We're investing in essential upgrades at Cheam Treatment Works in Sutton, replacing ageing pipework associated with the site's water softening process. The new pipework will be more resistant and will help improve the resilience of the treatment process.
Why we're carrying out this work
We're upgrading infrastructure used in the water softening process at Cheam Treatment Works. The existing equipment has experienced several failures in recent years, which can disrupt operations while repairs are carried out. This investment will improve reliability, reduce the need for reactive maintenance and help ensure customers continue to receive a consistent supply of softened water.
What customers may notice
During the works, customers supplied by Cheam Treatment Works may temporarily receive harder water than usual while the softening process is unavailable. Water quality will not be affected, and the water will remain safe to drink, although customers may notice increased limescale build-up on kettles, taps and appliances until the work is complete. We'll continue to provide updates throughout the project to keep customers informed of progress and key milestones.
Project timeline
Construction has already started and is expected to be completed by 27 January 2027.